Construction Updates: Pentagon Centre
This page hosts the periodic construction updates provided by Kimco for the “Milton” building at Pentagon Centre at 15th & Hayes street.
February 27, 2022
Hello Neighbors of Pentagon Centre
KIMCO Realty and Bozzuto Construction are continuing the Pentagon Centre – Building C project, also known as, “The Milton”.
February:
Below is a quick summary of ongoing and upcoming dates and impacts for remainder of February and beyond.
- Concrete Completion Date – March 04, 2022
- Washington Gas Utility Installation – COMPLETE
- Window Installation:
- Projected Start date – March 03, 2022.
- Projected Completion date – June 01, 2022
- Exterior Brick/Cladding:
- Projected Start date – January 07, 2022.
- Projected Completion date – October 28, 2022
- Tower Crane Removal – July 13, 2022, thru July 26, 2022
- Grant Street Traffic Signal Installation:
- Projected Start date – May 13, 2022.
- Projected Completion date – Aug 15, 2022.
- From grade to completion.
- Projected completion date – February 21, 2023
- Modified pedestrian and vehicular travel on 15th street and S. Hayes Street.
- Please continue to watch for posted directional signage.
If you have any further questions, please call 301-220-0100. This number is also posted around the project site fence.
We appreciate your continued patience, cooperation, and understanding.