Construction Updates: Pentagon Centre

This page hosts the periodic construction updates provided by Kimco for the “Milton” building at Pentagon Centre at 15th & Hayes street.


February 27, 2022

Hello Neighbors of Pentagon Centre

KIMCO Realty and Bozzuto Construction are continuing the Pentagon Centre – Building C project, also known as, “The Milton”.

February:

Below is a quick summary of ongoing and upcoming dates and impacts for remainder of February and beyond.

  • Concrete Completion Date – March 04, 2022
  • Washington Gas Utility Installation – COMPLETE
  • Window Installation:
    • Projected Start date – March 03, 2022.
    • Projected Completion date – June 01, 2022
  • Exterior Brick/Cladding:
    • Projected Start date – January 07, 2022.
    • Projected Completion date – October 28, 2022
  • Tower Crane Removal – July 13, 2022, thru July 26, 2022
  • Grant Street Traffic Signal Installation:
    • Projected Start date – May 13, 2022.
    • Projected Completion date – Aug 15, 2022.
  • From grade to completion.
    • Projected completion date – February 21, 2023
  • Modified pedestrian and vehicular travel on 15th street and S. Hayes Street.
  • Please continue to watch for posted directional signage.

If you have any further questions, please call 301-220-0100. This number is also posted around the project site fence.

We appreciate your continued patience, cooperation, and understanding.